The new library is under construction at 500 Hempstead Avenue

aug-firststeel
August 16- The first steel
is set in place!
20060817-12
August 17 – Structural Steel
erection continues...
  20060810-10
August 10: First structural steel delivery to site
20060816-11
August 16: Crane unloads steel delivery


20060810-9
August 10, 2006 – Underground storm drainage at SOG
  20060804-7
August 4: Column footing at SOG being poured
20060808-8
August 8: Concrete pier formwork completed.
20060803-5
August 3: Backfill near completion
at slab on ground (SOG).
20060804-6
August 4: Concrete pour for pier footings.
20060801-3
August 1: Steel fabrication at
Babylon Iron Works
20060801-4
August 1: Fabricated steel ready
for paint
  20060801-1
August 1: Backfilling and compaction for slab on ground (SOG) piers.
20060801-2
August 1: Compaction along column “D” wall

 

July 26-2

July 26: Anchor bolt survey markings

July 31

July 31: Anchor bolt surveyors in
main basement

 

July24

July 24: South basement concrete slab pour

July 26-1

July 26: Completion of the basement concrete slab

July 18-2

July 18: Completion of the south basement sub-grade

July 18-3

July 18: Another view

 

July 14

July 14: Crane delivers equipment
for sub-grade preparation

July 18-1

July 18: Crane delivers RCA for
sub-grade preparation

 

July 13-1

July 13: Steel delivery for WHPL at Babylon Iron's yard

July 13-2

July 13: Steel beams being prepared for fabrication

July11

July 11: Electricians perform backfill & compaction

July 11: Final foundation wall is completed
 

July5

July 5: Underground electrical conduit installations

July10

July 10: Foundation waterproofing begins

May 18, 2006- June 26, 2006

Work has progressed steadily preparing the library's foundation.

June26
  June20-b June22
  June15 June20-a
  June13
  June8 June12
May31 June1
  May18 May24

May 18, 2006

Foundation formwork removed after pour

Foundation after pour

May 8, 2006

Foundation wall formwork installed -
East Elevation

Foundation wall formwork

May 2, 2006


Today, at approximately 12:30 pm, the first pour on the footings of the new WHPL were laid into place. The new West Hempstead Public Library is born!

First Pour

May 2, 2006

Installation of footing formwork

Footing formwork installation
April 30, 2006
Groundbreaking Ceremony
Go back to MILESTONES
Before March 2006
After March 2006
Gas Station Gas Station Before Gas Station After March
Northwest Elevation NW Elevation Before NW Elevation After March
Southwest Elevation SW Elevation Before SW Elevation After March